Major reconstruction of streets and alleys within...
Major reconstruction of streets and alleys within the Downtown area
is in progress and will continue through May. Along with the street
work, overhead utilities are being moved under ground and various
sections of sewer lines are being replaced. The combined projects
will have one or two streets impacted on a daily basis throughout the
next four months.
Overhead utilities will be placed under ground on Park Avenue
through the middle of February. The work will involve periodic lane
closures just below Skyline Drive.
Beginning on Feb. 9, work will occur on Vista Lane and proceed
toward Mystic Way. Work on Mystic Way will begin just below the
intersection with Mystic View and proceed toward Hilledge Drive.
Street closures of about 100 feet in length will move down Mystic
Way, approaching Hilledge drive over the next few weeks.
Overhead utilities will be placed underground through May within
the Mystic Hills area. Work is underway on Hilledge Drive and will be
progressing upward. The major traffic impacts will occur when the
work is done on Skyline Drive in February and March.